Industry Confirms Australia’s Hobart Class Destroyers $870 Million Over Budget, Lead Ship 30 Months Late
SYDNEY, AUSTRALIA — The consortium building three air warfare
destroyers (AWDs) for the Royal Australian Navy has provided an update
on the construction of the ships, as well as an overview on the lessons
learned from the delays and cost overruns that have plagued the program.
Speaking at a conference on the sidelines of the Pacific 2015
International Maritime Exposition in Sydney, Australia, Rod Equid, chief
executive officer of the AWD Alliance, also touted steady progress on
the remaining two ships even as the lead ship, HMAS Hobart nears
completion.
The ships were ordered as part of Australia’s SEA 4000 program for a
new class of AWDs to replace the Royal Australian Navy’s Adelaide-class
(Oliver Hazard Perry) frigates and its stopgap air warfare capability
with the Raytheon SM-2 surface-to-air missile as part of requirements
outlined in the 2000 Australian Defense White Paper.
Australia’s Hobart-class AWDs are based on a Spanish Navantia F100
frigate hull modified to Australian requirements, chief of which is a
Lockheed-Martin Aegis combat system. Navantia’s design won selection as
the hull-form for the AWD in 2007, despite U.S naval company Gibbs and
Cox having previously been considered the favorite with an offer of an
evolved design based on scaled-down variant of the Arleigh-Burke Flight
II-class design.
The AWD Alliance is a contract arrangement between the Commonwealth
of Australia represented by the Capabilities and Sustainment Group
(formerly the Defense Matériel Organization) as owner-participant, ASC
and Raytheon Australia. Navantia, for its part, declined to be part of
the alliance, instead opting to sign a platform system design contract
with the Alliance.
Soon after construction on the AWDs began in 2010 with the
fabrication of pre-fabricated hull blocks at three widely-distributed
locations in Australia, reports began emerging of challenges facing the
process. These reportedly were primarily related to workforce
inexperience with Equid estimating that 95 percent of the workforce was
new hires who needed to be trained in the specialized roles they were
working in, but also because of issues with drawings available for the
alliance to work with.
These resulted in construction delays from the block subcontractors
at an early stage of the construction phase, which were exacerbated by
the typical “Ship One” issues and the high level of concurrency, which
had the effect delivering changes to production throughout construction.
The level of engineering effort was underestimated from the start, with
project schedules turning out to be too optimistic.
Overall, it was estimated that the construction schedule for the lead
AWD, Hobart, has slipped by approximately 30 months, with Equid
confirming that costs had overrun to the tune of $870 million. He also
touted improvements as the alliance gains experience from ship to ship,
citing a 30 percent improvement in second AWD (Brisbane) over the first,
with a further 20 percent improvement seen in the construction in the
third ship, Sydney.
The schedule was now more realistic and on plan, with the Hobart now
in the water since May 2015 with the ship then 76 percent complete.
Hobart will commence sea trials in Sept 2016, with delivery to the RAN
scheduled for July 2017. Brisbane is now 68 percent complete and close
to achieving the construction milestone of completing hull integration
with a planned delivery date of September 2018.
Moving on to lessons learned, Equid cited the age-old points of
having a realistic plan that matched the complexity of the undertaking
and the need to better manage concurrency of design-design maturity
issues. The problems with having a transactional relationship with
Navantia, where the Spanish shipyard opted out of the alliance and
instead signed a relatively low-value contract providing services was
cited, but deemed “unavoidable” by Equid.
A 2014 Australian National Audit Office report explained this
situation, saying that “there was limited incentive for Navantia to put
its own profit share at risk by entering an alliance agreement with a
new shipbuilder, and taking part in a pain-share gain-share regime it
imposed on (its) potential profit,” with the result of this was that it
detracted the ability of the alliance to collectively and
collaboratively manage risk.
A recent plan to advance the schedule for building frigates and
offshore patrol vessels under Projects SEA 5000 and SEA 1180
respectively and to emphasize domestic production effectively commits
the government to a permanent naval shipbuilding industry in Australia,
and would hopefully see the skilled labor issues that bedevilled the
early construction stages of the AWD program not be repeated in future
Australian naval shipbuilding programs.
However, although that decision was made before Australia’s recent
prime ministerial changes, with current Prime Minister Malcolm Turnbull
not having committed to the continuous-build plan since taking office in
September.
Source: USNI News.
No comments:
Post a Comment